12 Jan 2018 DECISION N°2018-0017/ARCOP/ORD DU 12 JANVIER 2018 SUR RECOURS DE GENERAL DE PRESTATION DE SERVICES SARL CONTRE LES RESULTATS PROVISOIRES DE LA DEMANDE DE PRIX N°2017-010/MESRSI/DG/UNZ/P/PRM DU 21 NOVEMBRE 2017 POUR L’ENTRETIEN ET LE NETTOYAGE DES BATIMENTS DE L’UNIVERSITE NORBERT ZONGO.
12 Jan 2018 DECISION N°2018-0016/ARCOP/ORD DU 12 JANVIER 2018 SUR RECOURS DE ETY SARL CONTRE LES RESULTATS PROVISOIRES DE L’APPEL D’OFFRES OUVERT ACCELERE N°2018-02/MS/SG/CHUSS/DG/PRM A ORDRE DE COMMANDE POUR LA CONCESSION DE L’ENTRETIEN ET DU NETTOYAGE AU PROFIT DU CENTRE HOSPITALIER UNIVERSITAIRE SOURO SANON (LOT 01).
10 Jan 2018 PROCES-VERBAL DE CONCILIATION N°2018-0015/ARCOP/ORD DU 10 JANVIER 2018 SUR DEMANDE DE CONCILIATION DE LA SOCIETE SO.COM.CO AVEC LA COMMUNE DE YAKO DANS LE CADRE DE L’EXECUTION DES LETTRES DE COMMANDES N°CO/09/10/03/02/00/2017/00011 ET N°CO/09/10/03/02/00/2017/00012 SUIVANT DEMANDE DE PRIX, POUR LA CONSTRUCTION CHACUNE D’UN BLOC DE TROIS (03) SALLES DE CLASSE + BUREAU + MAGASIN A L’ECOLE DE PETIT-SAMBA ET DU SECTEUR 4 DANS LADITE COMMUNE
10 Jan 2018 PROCES-VERBAL DE NON CONCILIATION N°2018-0014/ARCOP/ORD DU 10 JANVIER 2018 SUR DEMANDE DE CONCILIATION DU CONSULTANT OUEDRAOGO OUSMANE AVEC LA COMMUNE DE YAKO DANS LE CADRE DE L’EXECUTION DE LA MANIFESTATION D’INTERET POUR LE SUIVI-CONTROLE DES TRAVAUX DE CONSTRUCTION DE TRENTE-HUIT (38) BOUTIQUES AU PROFIT DE LADITE COMMUNE
10 Jan 2018 PROCES-VERBAL DE CONCILIATION N°2018-0013/ARCOP/ORD DU 10 JANVIER 2018 SUR DEMANDE DE CONCILIATION DU CONSULTANT OUEDRAOGO OUSMANE AVEC LA COMMUNE DE YAKO DANS LE CADRE DE L’EXECUTION DE LA LETTRE DE COMMANDE CO/09/10/02/03/00/2016/00010 POUR LE SUIVI-CONTROLE DES TRAVAUX DE CONSTRUCTION D’UNE ECOLE A TROIS (03) SALLES + BUREAU + MAGASIN + LATRINE QUATRE (04) POSTES AU SECTEUR 7 (ZINIGUIM) DANS LADITE COMMUNE.
10 Jan 2018 PROCES-VERBAL DE NON CONCILIATION N°2018-0012/ARCOP/ORD DU 10 JANVIER 2018 SUR DEMANDE DE CONCILIATION DU CABINET D’AVOCATS MAITRE ELIANE MARIE NATACHA KABORE, AGISSANT AU NOM ET POUR LE COMPTE DE SOCIAB AVEC LA COMMUNE DE POUNI DANS LE CADRE DE L’EXECUTION DU MARCHE N°ED/01/03/01/10/2017/0008 SUR ENTENTE DIRECTE N°2017-03/RCOS/PSNG/CR-PUN POUR LA FOURNITURE DE VIVRES AU PROFIT DE LADITE COMMUNE
10 Jan 2018 PROCES-VERBAL DE CONCILIATION N°2018-0011/ARCOP/ORD DU 10 JANVIER 2018 SUR DEMANDE DE CONCILIATION DE L’ENTREPRISE LP COMMERCE AVEC LA COMMUNE DE BOBO-DIOULASSO DANS LE CADRE DE L’EXECUTION DE LA DEMANDE DE PRIX N°2017/02/CB/M/SG/CCAM POUR L’ACQUISITION DE PRODUITS D’ENTRETIEN MENAGER AU PROFIT DE LA MAIRIE CENTRALE ET DES FORMATIONS SANITAIRES DE BOBO-DIOULASSO.
10 Jan 2018 PROCES-VERBAL DE CONCILIATION N°2018-0010/ARCOP/ORD DU 10 JANVIER 2018 SUR DEMANDE DE CONCILIATION DU CABINET GOUNFO SOLANGE ZEBA, AGISSANT AU NOM ET POUR LE COMPTE DE L’ENTREPRISE GAUTH AVEC LA COMMUNE DE NIANGOLOKO DANS LE CADRE DE L’EXECUTION DU MARCHE N°09-CO/02/03/01/00/2014/00023 POUR LA CONSTRUCTION D’UN COMPLEXE SCOLAIRE ET DE LATRINES A QUATRE (04) POSTES A KITODOUGOU DANS LADITE COMMUNE
10 Jan 2018 DECISION N°2018-0009/ARCOP/ORD DU 10 JANVIER 2018 SUR RECOURS DU GROUPEMENT TSK ELECTRONICA Y ELECTRICIDAD SA-ACCESS INFRA AFICA LLC-ENERGY EXPERTS NOW SA CONTRE LES RESULTATS PROVISOIRES DE L’APPEL D’OFFRES N°017-0389/ME/SG/DMP DU 06 NOVEMBRE 2017 POUR LA SELECTION D’UN PARTENAIRE PRIVE FAISANT SUITE A LA MANIFESTATION D’INTERET N°2016-022/MEMC/SG DMP DU 23 NOVEMBRE 2016 POUR LA REALISATION D’UNE CENTRALE THERMIQUE DE FUEL LOURD DE PRODUCTION D’ELECTRICITE DE 100 MEGAWATTS (MW) EXTENSIBLE A 150 MW A OUAGADOUGOU.
10 Jan 2018 DECISION N°2018-0008/ARCOP/ORD DU 10 JANVIER 2018 SUR RECOURS DE SENEF CONTRE LES RESULTATS PROVISOIRES DE L’APPEL D’OFFRES ACCELERE N°2018-02/CO/M/CB/DCP POUR L’ENTRETIEN ET LE NETTOYAGE D’INFRASTRUCTURES DE LA COMMUNE DE OUAGADOUGOU (LOTS 04 ET 07).